Annual Surface Transportation Infrastructure Report 2025
ID 377248090 © Dr. Victor Wong | Dreamstime.com

Policy Brief

Annual Surface Transportation Infrastructure Report 2025

It was a strong year for global public-private partnership activity with 43 surface transportation project closings worth $11.9 billion.

Introduction

Governments have used long-term public-private partnerships for surface transportation projects for the past 60 years.

As documented by José A. Gómez-Ibáñez and John Meyer, the phenomenon began in the 1950s and 1960s, as France and Spain emulated the model pioneered by Italy prior to World War II. Italy’s national motorway systems were developed largely by investor-owned or state-owned companies operating under long-term franchises (called concessions in Europe).

In exchange for the right to build, operate, and maintain the highway for a period ranging from 30 to 70 years, the company could raise the capital needed to build it (typically a mix of debt and equity).

The model spread to Australia and parts of Asia in the 1980s and 1990s, and to Latin America in the 1990s and 2000s. Nearly all the projects in those regions from the 1950s to 1980s were financed based on the projected toll revenues to be generated once the highway was in operation.

Some projects went bankrupt as a consequence of reduced traffic and revenues during severe economic downturns (e.g., the oil price shock of 1974), leading to the nationalization of some companies.

However, in the late 1990s and early 2000s, the governments of France, Italy, Portugal, and Spain all privatized their state-owned toll road companies and formalized the toll concession P3 model.

Australia has allowed several concession company entities to go through liquidation, with the assets (in each case major highway tunnels) being acquired by new operators at a large discount from the initial construction cost.

Other governments in Europe adopted a different form of highway concession. Generally, not favoring the use of tolls, they created the concept of availability payments as a means of financing long-term concession projects.

In this structure, the company or consortium selected via a competitive process negotiates a stream of annual payments from the government sufficient (the company expects) to cover the capital and operating costs of the project and make a reasonable profit. The capital markets generally find such a concession agreement compatible with financing the project via a mix of debt and equity. Since no toll revenues are involved, this model applies to a much broader array of transport and facility projects, including rail transit. In the highway sector, nearly all long-term concession P3 projects in Canada, Germany, the United Kingdom, and a number of Central and Eastern European countries have been procured and financed as availability payment (AP) concessions.

In a small but growing number of cases—major bridges, as well as highway reconstruction that includes added express toll lanes, for example—governments collect the toll revenues and use the money to help meet their availability payment obligations. These cases are called “hybrid concessions” in this report.

Of the top 10 worldwide surface transportation P3s that reached financial close in 2024, four used availability payments, bucking what had been a growing trend over the last seven years. In 2023, seven of the top 10 P3s used availability payments.

The growing use of AP concessions has enabled P3s for projects that do not generate their own revenues, as well as hybrid concessions in which toll revenues help the government cover the costs of its AP obligations.

For the past seven years, almost three-quarters of the largest P3 projects, by financial value, have used availability payment public-private partnerships.

Annual Surface Transportation Infrastructure Report 2025